Getting AroundTop story
Construction on the $123 million Cortez Bridge replacement began Monday
The new Cortez Bridge will be 65 feet tall and cost $123 million
- $123 million
- for the replacement project
- 65 feet
- tall, the new fixed-span bridge
- 0.9 miles
- from 123rd Street West to Gulf Drive
- 1,200 days
- the project is expected to last, approximately
If you cross to Anna Maria Island, the Cortez Bridge replacement is officially underway. The Florida Department of Transportation began construction Monday on a fixed-span bridge that will sit next to the current drawbridge. It'll have two travel lanes each way and protected sidewalks, which doubles the drawbridge's capacity, and the target finish is summer 2030.
- Phase 1: Crews build the northern half beside the old bridge
- Phase 2: Traffic shifts, old bridge comes down, southern half goes up
- Boaters: Intracoastal Waterway stays open; drawbridge schedule unchanged
- Traffic: Lane closures, shoulder closures and shifts throughout construction
Crews start with pile driving and utility work along the Hunters Point property. Construction runs 7 a.m. to 6:30 p.m., with occasional night and weekend work.
Cortez Bridge construction is scheduled 7 a.m. to 6:30 p.m.
Cortez Road Bridge replacement work zone, Cortez to Bradenton Beach
- 7 a.m. to 6:30 p.m.Scheduled construction hours
- Also
- Occasional night and weekend work
- Lane closures
- Intermittent, day and night
Source: Anna Maria Island Sun
View as table
| When | What |
|---|---|
| 7 a.m. to 6:30 p.m. | Scheduled construction hours |
| Also | Occasional night and weekend work |
| Lane closures | Intermittent, day and night |
Business owners are watching. Max Tanski of The Fox Mercantile said he was shocked by the traffic out of season, and Sam Varelis of Cortez Cafe expects to lose some customers. Tanski's pitch: “Don’t let it deter you. Make the trip over.” FDOT says the job will take about 1,200 days.