Manatee County approves more than $100 million in projects to fight flooding after Debby, Helene and Milton
Two automated outfall projects top the approved spending
Source: Beacon Media
View as table
| Value | |
|---|---|
| Pearce Drain outfalls | $24.9M |
| Bowlees Creek outfalls | $19.1M |
| Meadors/Pennsylvania | $11.3M |
| Sylvan Oaks stormwater | $8M |
| Cortez Road | $6.5M |
If flooding worries you, here's what's coming. County commissioners approved the first round of projects under the Lasting Manatee Infrastructure Recovery and Resiliency Program. It's paid for from the county's $252.7 million federal disaster-recovery grant and covers drainage, stormwater, water and wastewater systems, and critical public facilities.
- Bradenton: five projects, including $3,650,000 for Second Avenue drainage
- Palmetto: $3,619,000 for wastewater plant expansion, Phase 1
- Not yet: federal reviews and agreements come before money is spent
Tom Gerstenberger, engineering division manager for Manatee County Public Works, told ABC7 that six public works projects in eligible low- and moderate-income areas, including Center Lake and Shady Brook, get about $66 million. Automated outfall structures are gates that let the county lower water levels ahead of a storm. The technology can't eliminate flooding. You can explore approved projects on Lasting Manatee's program map.
The recovery program by the numbers
- $252.7 million
- in federal disaster-recovery grant money for the county
- $125 million
- the most the county set aside for this program
- $66 million
- approximately, for six public works projects
- 15
- automated outfall structures already installed
Sources: Beacon Media, mysuncoast.com